Western Australia's Government reported (11-Jul-2019) tunnel boring machine (TBM) 'Sandy' reached Redcliffe Station. Since boring began in late 2017, TBM Sandy has tunnelled more than 4.5km and installed more than 2750 rings to form Tunnel Two. Construction of the area where passengers will enter Forrestfield Station is now underway, with installation of structural steel for the lower roof almost complete. Additionally, brickwork and installation of door frames are also in progress. [more - original PR]